US Grid Operators Offer Data Centres Faster Power Hookups in Exchange for Flexibility and Guarantees

Ohio, Texas and the Southwest Power Pool are trading quicker connections for minimum payments or curtailment rights, while FERC has pushed PJM's version back to the states.

Aerial view of data center campuses in Ashburn, Virginia
Data center campuses in Ashburn, Virginia, one of the world's largest data center clusters. Photo: Theodore Christopher / Wikimedia Commons (CC0) (file)

WASHINGTON – US utilities and grid operators are setting up ways for data centres to connect faster in return for commitments that reduce the risk they pose to the grid. Instead of waiting years for upgrades or building private power plants, developers can guarantee payments, accept curtailment or bring their own capacity.

Highlights

  • Ohio large loads must pay for up to 85% of subscribed capacity.
  • ERCOT offers earlier energisation for loads accepting dispatchable curtailment.
  • SPP promises 90-day studies for loads that accept remote disconnection.
  • FERC rejected most of PJM’s interim large-load plan on 9 October.

Paying for what you reserve

In Ohio, regulators approved a settlement after AEP Ohio proposed a data-centre tariff. Large customers must pay for up to 85% of their subscribed capacity even if they use less, with longer contracts and extra collateral. In return, a connection moratorium was lifted.

The aim is to stop existing customers paying for infrastructure built for speculative projects that never arrive.

Controllable load

The Electric Reliability Council of Texas (ERCOT) requires large facilities to meet ride-through standards. Under its new Batch Zero process, developers can choose curtailment under ERCOT’s real-time control in exchange for earlier connection. The Southwest Power Pool’s High Impact Large Load framework offers interconnection studies within 90 days to developers that accept real-time forecast reporting, ramp-rate limits and remote-disconnect capability.

PJM sent back to the states

PJM Interconnection proposed letting large loads connect without matching new capacity if they agreed to be curtailed before grid emergencies. On 9 October, FERC rejected most of the plan, saying it intruded on state authority over retail customers and appeared discriminatory, Utility Dive reported. FERC accepted PJM’s definition of large loads and a registry.

It “strongly” encouraged states to decide which retail customers are curtailed first. Jefferies analysts said the ruling could keep PJM capacity prices higher for longer, which favours independent power producers.

“We need state regulators to establish clear rules for which customers should be curtailed first,” FERC commissioner David Rosner said.

The common thread

Seyed Madaeni, chief executive of battery-software company Verse, argued in a Utility Dive opinion piece that the question in each market is the same: “What can a data center guarantee in exchange for access to power?” FERC in June directed all six regional grid operators under its jurisdiction to justify or reform their large-load tariffs.

For developers, the rules still vary widely between utilities, so the cost of faster power is hard to compare before choosing a site. For existing customers, the guarantees are meant to protect bills and reliability as demand grows.