Fervo’s Contracted Revenue Jumps to $11.9 Billion After Record Google Geothermal Deal
The enhanced geothermal developer brought its first Utah unit into commercial operation and says its Cape Station site could support 8.4GW.
HOUSTON, United States – Fervo Energy said its contracted revenue rose to about $11.9 billion at the end of September, from $7.2 billion three months earlier. The rise follows a 396MW power purchase agreement with Google, which the enhanced geothermal developer believes is the largest of its kind.
Highlights
- Contracted capacity rose to 1,054MW from 658MW in the quarter.
- Google deal is a 15-year, take-or-pay contract for 396MW.
- First 33MW GeoBlock at Cape Station began commercial operation.
- Second-half capex guidance cut to $700-$750 million on efficiencies.
The Google deal
The grid-connected contract covers eight GeoBlocks at Cape Station in Utah, now called Cape Google 400, with first power expected in mid-2028 and full capacity by the end of that year. Fervo has also committed to offer Google an option for about 600MW more, taking the partnership to nearly 1GW. For that expansion, the two are pursuing direct delivery to a potential data centre in Beaver County under Utah’s SB132 framework.
Because the contract is grid-connected, Google can take the power or sell it on if it is not ready to use it, chief executive Tim Latimer said on the earnings call, according to TechCrunch. “Google can develop a potential data center on their schedule, and neither party is waiting on the other,” he said.
Operations
Fervo declared commercial operation at the 33MW GeoBlock 1 on September 30, ahead of its contractual date. GeoBlock 2 is delivering test energy and GeoBlock 3 is in commissioning; both are due to start commercial operation by January 1, 2027, completing the roughly 100MW first phase. An independent study by DeGolyer and MacNaughton now puts Cape Station’s potential at about 8.4GW, nearly double the earlier 4.3GW estimate.
Costs and finances
The first phase costs about $7,000 per kilowatt. Fervo targets $5,500 per kilowatt for Cape Google 400 and $3,000 in the long term. TechCrunch said the Google project’s cost is, with subsidies, roughly equivalent to a new gas plant running on fuel at $6 per million BTUs.
Fervo reported an operating loss of $43.7 million for the quarter. It ended September with $1.9 billion of unrestricted cash and $301.6 million of debt. It expects fourth-quarter capital spending of $450 million to $500 million and was selected for two potential Department of Energy awards worth about $20 million.
Why it matters
The Google contract shows a hyperscaler locking in always-on clean power for AI demand years before it is delivered. Fervo’s next test is cost: reaching $5,500 per kilowatt at Cape Google 400 would make geothermal more competitive with gas, while the $3,000 target would go further. Delivering GeoBlocks 2 and 3 on time by January would also support its case as a dependable supplier.
Sources
- TechCrunch: Fervo now has $12B in orders for its geothermal power tech
- Fervo Energy: Reports Third Quarter 2026 Results
Written by
Tumisang Bogwasi
Tumisang Bogwasi, Founder & CEO of Brimco. 2X Award-Winning Entrepreneur. It all started with a popsicle stand.
