Guinea Grants PDI Gold’s Bankan Mining Permit After a Wait of Nearly Two Years
The exploitation permit clears the last regulatory hurdle for the $463 million Bankan gold project. PDI says construction could start within four to six weeks.
CONAKRY, Guinea – Guinea has granted PDI Gold the exploitation permit for its Bankan gold project, ending a wait of nearly two years. The permit clears the final regulatory hurdle for one of West Africa’s largest undeveloped gold mines, Reuters reported.
Highlights
- Guinea has granted an exploitation permit for PDI Gold’s Bankan gold project after a wait of nearly two years.
- The permit clears the final regulatory hurdle for the $463 million project, Reuters reported.
- Chief executive Matthew Wilcox said construction could start in four to six weeks, with first gold about 18 months later.
- Guinea also approved permits for the Mansounia deposit, which will expand production at PDI’s Kiniero mine.
- PDI expects first Bankan gold in mid-2028 and average production of about 250,000 ounces a year over 12 years.
Key numbers (PDI Gold and Reuters, 17 November 2026)
- Bankan project cost: $463 million
- Permit area and term: 98.6 square kilometres, an initial 15 years
- Expected jobs: about 2,000 in construction and 1,000 permanent
- Expected taxes, royalties and state-carried interest: more than $5 billion over the mine’s life
The permits
The Bankan permit was issued under presidential decree D/2026/356/PRG/SGG, dated 16 November, and is held by Hamana Gold SA, PDI said in its announcement to the Australian Securities Exchange. It covers 98.6 square kilometres for an initial term of 15 years.
Guinea also approved two permits for the Mansounia satellite deposit, issued under decrees D/2026/357/PRG/SGG and D/2026/355/PRG/SGG, also dated 16 November. They are held by Sycamore Mine Guinee SAU.
The two Mansounia permits cover 44.7 and 26.5 square kilometres, each for an initial 15 years.
Under Guinea’s Mining Code, the government is entitled to a 15% interest in the exploitation permits.
Moving to construction
PDI chief executive Matthew Wilcox told Reuters that Bankan is fully financed and would move quickly into development. “We’ll probably start construction in the next four to six weeks,” he said.
Wilcox said he expects first gold about 18 months after construction starts.
A June 2025 feasibility study outlined average production of about 250,000 ounces a year over 12 years.
All-in sustaining costs were estimated at $1,111 an ounce, at a gold price of $3,300 an ounce.
PDI said it has already made $18 million in down payments for a SAG mill, a ball mill and a 40-megawatt power station. The board has authorised the company to accelerate procurement, detailed engineering and compensation work so construction can start as soon as practicable.
The company expects to publish an optimised construction schedule, capital estimate and production profile in early 2027. Based on work to date, it said the optimised schedule should allow first gold in mid-2028, and that it does not expect the $463 million capital cost in the feasibility study to rise.
Together with Kiniero, PDI is targeting more than 400,000 ounces a year once Bankan is in full operation.
Mansounia and Kiniero
Mansounia has a probable ore reserve of 19.5 million tonnes at 0.77 grams of gold a tonne. That is equivalent to about 0.48 million ounces.
PDI describes the deposit as near-surface, with a low stripping ratio, and said it has already completed extensive grade-control drilling and initial pit designs. Kiniero poured first gold in December 2025 and reached commercial production in February 2026.
The company said Kiniero is on track for 2026 guidance of 157,000 to 174,000 ounces.
A backlog that has worried miners
Industry executives told Reuters that exploration and mining permits in Guinea have effectively been stalled for more than two years. Some companies have had to revise mine plans, process lower-grade ore or slow production.
Guinea’s mines minister, Bouna Sylla, acknowledged the delays. “Companies apply through the mining commission,” he said. “Sometimes there is back-and-forth with the mining commission, but we are working to resolve those issues soon.”
Why it matters for business
The permit is a test of whether Guinea is clearing its backlog, which has weighed on investment in both gold and bauxite. Contractors, equipment suppliers and lenders across West Africa will watch whether other long-pending applications now move.
The award lands in a busy week for African gold, with Perenti winning a new A$1 billion contract at Tanzania’s Geita mine.
It also comes as new domestic refining rules leave some Guinea gold producers, including PDI, holding unsold bullion, Reuters reported.
Sources
- PDI Gold Limited, ASX announcement: Bankan and Mansounia Exploitation Permits Granted (17 November 2026)
- Reuters via Mining Weekly: Guinea clears PDI Gold permit, raising hopes of easing mining backlog (17 November 2026)
- Listcorp: Bankan and Mansounia Exploitation Permits Granted, PDI Gold Limited (ASX:PDI) (17 November 2026)
- Reuters via MarketScreener: Guinea grants permit to PDI Gold, potentially easing miners’ concerns (17 November 2026)