Energy minister Kgosientsho Ramokgopa will publish a "case for nuclear" paper this month to head off the litigation that sank earlier plans; Eskom has picked Duynefontein and Thyspunt.

Koeberg nuclear power station near Cape Town
Koeberg nuclear power station, South Africa's only nuclear plant, near Cape Town. Photo: Paul Scott / Wikimedia Commons (CC BY-SA 2.0) (file)

PRETORIA, South Africa – South Africa will publish a position paper making the “case for nuclear” at the end of November, Energy Minister Kgosientsho Ramokgopa said. The paper is the first step towards procuring 5.2 gigawatts of new nuclear capacity, and Eskom says the first new reactor could be online by around 2036.

Highlights

  • Position paper due end-November, with 60 days for public comment.
  • Ramokgopa aims for a section 34 determination by mid-2027.
  • Eskom has selected Duynefontein and Thyspunt as sites.

A plan built to survive court

Speaking at the Nuclear and Clean Energy Conference in Irene on Tuesday, Ramokgopa said the paper would accompany a proposed determination under section 34 of the Electricity Regulation Act. Its aim is to head off the legal challenges that have stalled earlier attempts, TechCentral reported. “We are going to build nuclear in this country. Take us to court,” he said.

He told reporters he was aiming for a determination in April 2027, and in his speech said the final document would be published “before June of 2027”. He conceded the extra step would add four to six months to the programme. In August 2024 he withdrew a 2.5GW determination after the DA, now part of the government of national unity, launched a legal challenge.

The 5.2GW in the 2025 Integrated Resource Plan is a first phase, Ramokgopa said. He wants to expand it to 10GW.

Sites and timeline

Eskom group chief executive Dan Marokane confirmed Duynefontein, next to Koeberg in the Western Cape, and Thyspunt in the Eastern Cape as the selected sites. “We’re working on roughly a 10-year timeline, so potentially by 2036 the first reactor could come online,” he said.

Thyspunt carries legal risk. It holds provisional Grade I heritage protection until February 1, 2027, which can be renewed, and Earthlife Africa has long opposed the site. In May, Eskom proposed 4.8GW from conventional pressurised water reactors and 400MW from small modular reactors.

Who owns and who pays

Ramokgopa said all nuclear assets would stay in state hands through Eskom, with “no room for the privatisation of the space.” Funding options under study could include private-sector participation.

The price, funding structure and tariff impact have not been disclosed, TechCabal noted. Ramokgopa himself cited Eskom’s troubled Medupi and Kusile coal plants as examples of how not to run a major build.

Why it matters

South Africa has not built a nuclear plant in four decades, since Koeberg. The undisclosed cost and financing, and the risk of further court challenges, will decide whether the 2036 timeline holds.