Africa Companies

Allied Gold Moves Kurmuk Toward Commercial Production as Ethiopia Grid Work Begins

Allied Gold is installing the last grid equipment at Ethiopia's Kurmuk gold mine, targeting first sales in December and commercial production by year-end.

The processing plant at Allied Gold's Kurmuk mine in Ethiopia
The processing plant at Allied Gold's Kurmuk mine in Ethiopia. Photo: Allied Gold

KURMUK, Ethiopia – Allied Gold is installing the last grid equipment needed to run its Kurmuk gold plant in Ethiopia at full power, and is targeting commercial production before the end of 2026. The company said on 18 November that Ethiopian Electric Power’s contractor had begun assembling and commissioning an automated grid-stabilisation system.

Highlights

  • Ethiopian Electric Power’s contractor has begun installing an automated grid-stabilisation system at Kurmuk.
  • Allied Gold is targeting first gold sales in December 2026 and commercial production by year-end.
  • The company poured first gold at Kurmuk on 9 November, it said in an earlier announcement.
  • An initial resource estimate for the Tsenge Trend’s Kiftet and Hiccup Hill zones is expected in the first half of 2027.

Key numbers (Allied Gold, 9 and 18 November 2026)

  • First gold poured: 9 November 2026
  • Gold sales targeted: December 2026
  • Commercial production targeted: by year-end 2026
  • 2026 production guidance: 25,000 to 35,000 ounces
  • Tsenge resource estimate: first half of 2027

The last step on power

The upgrade is meant to let the plant draw its normal load from Ethiopia’s national grid without relying on diesel generators. Allied Gold energised the mine’s grid connection in September.

"The system will ensure a stable, full-power draw from the grid, enabling sustainable increases in throughput," the company said in its 18 November statement.

First gold, then commercial production

Kurmuk poured first gold on 9 November. Allied Gold has not yet declared commercial production.

In that earlier announcement, the company said Kurmuk is expected to produce 25,000 to 35,000 ounces in 2026.

It also said production is expected to rise to 55,000 to 65,000 ounces in the first quarter of 2027.

Both December sales and a year-end commercial-production declaration still depend on commissioning and plant performance. The 18 November update did not change the November production guidance.

Tsenge and the longer production aim

Allied Gold is also advancing the Tsenge Trend, a nine-kilometre exploration corridor near the plant. An initial mineral resource estimate for the Kiftet and Hiccup Hill zones is expected in the first half of 2027.

The company is doing engineering and design work and preparing to start the permitting needed to develop Tsenge as extra mill feed. Tsenge remains at the exploration stage.

Allied Gold’s longer-term aim is to sustain production of about 300,000 ounces a year at Kurmuk by adding higher-grade ore as early feed from the Ashashire and Dish Mountain pits declines. Its 9 November release said Kurmuk is expected to average about 300,000 ounces a year over its first four years and 240,000 ounces a year over the life of the mine.

Why it matters

Reliable grid power is the last big operating hurdle before regular gold sales at a new Ethiopian mine. For Allied Gold, commercial production would start converting development spending into cash flow.

Contractors, power suppliers and other West African gold developers will watch whether the grid can actually run the plant at normal load, and whether Tsenge can extend the higher-grade years.

What to watch

The next tests are whether the stabilisation system is completed, whether gold sales start in December, and whether commercial production is declared by year-end. The Tsenge resource estimate in the first half of 2027 will show whether the plant can be fed for longer at higher grades.